Congratulations!
Congratulations!
Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.
Very nice. It's amazing how the clear water on the white plaster immediately begins to look blue.
Site owner -- www.troublefreepool.com
Funny you should say that Sean. My wife asked the same question. I had her...and her father believing that the PB added food coloring to the pool before they left yesterday :-)
They were a bit gullable on that one...i Loved it.
Then I showed them the on the web the real reason. They are still a bit mad at me :-)
Well...all done. Pool is filled and filter is running. Now to the landscaping. Going to do RiverRock around the pool..move the fence out..etc. There goes another 5k :-)
Then on to the closing the pool. We are going to run for 4 weeks...then close. Quick question though, do i need to monitor PH level during winter? I don't want to ruin the finish of the plaster.
thanks..Jerry
![]()