    Default Re: eljefe281's (Jeff's) pool project

    It's starting to look like something, with most of the coping in place.

    I feel sorry for my poor builder. I strongarmed him into ordering custom, double bullnosed coping pieces for the top of the raised beam and around the spa so we wouldn't have seams running lengthwise. There was some sort of miscommunication and not enough pieces got ordered, so now he's going to have to remobilize the coping guy next week.

    It amazes me that this guy doesn't blink an eye when something like this happens.

    There must be a whole lot of contingency in the contract price.
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  2. #2
    Join Date
    May 2006
    Location
    Connecticut
    Posts
    16

    Default Re: eljefe281's (Jeff's) pool project

    Is that a sewer line going through your pool?

  3. #3
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Yes, I thought I'd leave it in there to add some character.

    Actually, they completed the permanent reroute, but, for some reason, they haven't removed the temporary line yet.

    Maybe they don't want the cavities to get all full of heaven-knows-what.
    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  4. #4
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project

    Recent progress:







    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  5. #5
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project







    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  6. #6
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project







    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

  7. #7
    Join Date
    May 2006
    Location
    Sugar Land, Texas
    Posts
    183

    Default Re: eljefe281's (Jeff's) pool project





    Pool owner - contract signed 21Aug2006; HOA approval granted; complete - existing patio demolition; excavation; rebar; embedded plumbing; gunite; plumbing; electrical; tile and coping; decking; plaster; pool fill; acid start-up; regular start-up; pool school; gas meter upgrade; additional of salt; PDA remote programming.

+ Reply to Thread

Similar Threads

  1. AL's Pool Project 10-17-06
    By No Need in forum In-Ground Pool Construction and Repair
    Replies: 45
    Last Post: 04-08-2007, 10:06 AM
  2. Subcontracting your own pool project?
    By minddeal in forum In-Ground Pool Construction and Repair
    Replies: 14
    Last Post: 02-28-2007, 10:15 PM
  3. Steve's pool project 1-24-07
    By skamp in forum In-Ground Pool Construction and Repair
    Replies: 49
    Last Post: 02-20-2007, 02:30 PM
  4. That massive pool restoration project
    By peppercorn in forum In-Ground Pool Construction and Repair
    Replies: 8
    Last Post: 01-04-2007, 10:10 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts