Pool Layout
Just after Dig
Working on Steel
Plumbing Starting
The excavation started yesterday, Friday and they are anticipating Gunite next Tuesday. We'll see how it goes. The weather has been very good here for the past week or so.
Pool Layout
Just after Dig
Working on Steel
Plumbing Starting
The excavation started yesterday, Friday and they are anticipating Gunite next Tuesday. We'll see how it goes. The weather has been very good here for the past week or so.
Last edited by 26theone; 03-03-2007 at 10:03 AM.
Roger,
Congratulations!!!! Nice design and looks like it will tuck in your backyard with room to spare. What are all of the specs on your pool? Keep the pics coming.![]()
![]()
Nice design! Looks like they are on the way. Keep posting updates!
Steve
The gunite is complete and the equipment is installed. Next step is coping, tile, and electrical work.
Plumbing
![]()
Steel Complete
![]()
Gunite being applied
![]()
Gunite Complete
![]()
I have a sprinkler in the pool to wet the gunite every 6 hours or so.
We're debating Primera stone too, unfortunately there are very few pics of it availble, and the ones on wetedge's website are hard to judge by... My PB is filling a pool this week with it though, so we'll get to see at least one in person.
Tile, Coping and Electrical finished last week. I need to upload a new picture.
The deck forming should be completed today with the concrete pouring later this week if the weather holds out.
Interior pool finish and fill is scheduled for next week.
Then spray deck and cleanup.
We are looking at finishing in less than a month!
The deck concrete was poured today but it was too dark to take pictures. I have some other pictures of the progress. We are hoping to finish soon.
Spa
Deck Prep
Mission Control
Table Area
I have more pictures posted to http://stroudsonline.spaces.live.com