Thanks!

So, we had the sod removed last week, but I kept getting rained out on days I planned to work on leveling.

Well, we finally got to start yesterday (heat index of 110 degrees). About 4 inches down on the high side was a 4' x 10' slab of 10" thick concrete. Grrrrrr....

Took a big chunk of the afternoon to bust up the concrete and remove it.

Ended up getting a few of the blocks set for the posts using a laser transit level. Had to dig down a fair amount though, so we've got a fair amount of digging and raking left to do.

Back to the grind after work today.